Road Construction and Detours

Posted on: May 12, 2025

[ARCHIVED] Phase 2 Final Paving and Road Restoration - Monday 5/12

sewer update thumbnail

Today's anticipated daily paving schedule from 7AM - 5 PM: Monday, May 12: High Tide Lane and Cedar Way

Final paving and road restoration work in East Orleans is scheduled to begin this week.

Detour signage will be clearly posted, and onsite details/crews will be available to assist with safe navigation for both vehicles and pedestrians.

We appreciate your continued patience and cooperation as this important work progresses.

Please note that paving on Main Street remains on schedule for mid-June. Additional details will be provided in the coming weeks.


For questions, please contact the Town’s Water/Sewer Program Coordinator, John Nelson at (508) 240-3700, x2319 or at jnelson@town.orleans.ma.us, or Sewer Ombudsman, Martin “Reggie” Donoghue, AECOM (the Town’s engineering consultant) at (508) 237-7161 or rdonoghue@town.orleans.ma.us.